Kamoa Copper 220/33kV Substation

Client: ABB South Africa

Type: Electrification

Project Value: $ 35 million

Size: 17 100m²

Completed:  2021

Scope: Civil and Structural Design Work

Structural: Design of steel equipment supports, reinforced concrete pad foundations, reinforced concrete framed control building